Brigade Horizon Tower E: Milestone Release On commencement of Painting - Apr 2025
Brigade Horizon Tower E: Milestone Release On commencement of Painting - Apr 2025
Brigade Horizon Tower D: Milestone Release On Installation of Lift - Apr 2025
Brigade Horizon Tower F: Milestone Release On commencement of fixing of Doors and windows - Apr 2025
Brigade Horizon Tower F: Milestone Release On commencement of fixing of Doors and windows - Apr 2025
Entry Portal - Mar 2025
G & H Blocks: Elevation - Mar 2025
G & H Blocks: Elevation - Mar 2025
I Block: Work Status - Mar 2025
J & K Blocks: Elevation - Mar 2025
L Block: Elevation - Mar 2025
N Block: Work Status - Mar 2025
O Block: Elevation - Mar 2025
R Block: Elevation - Mar 2025
D Block: Elevation - Mar 2025
C Block: Elevation - Mar 2025
M, L & K Blocks: Elevation - Mar 2025
Q, P & O Blocks: Elevation - Mar 2025
View From South-East Corner - Mar 2025
East Elevation - Mar 2025
4 Acre: Podium, Staircases & Activity Lawn Area Finishing Works - Mar 2025
4 Acre: Podium, Staircases & Activity Lawn Area Finishing Works - Mar 2025
4 Acre: Podium, Staircases & Activity Lawn Area Finishing Works - Mar 2025
Elevation Wall Between Blocks R & E - Mar 2025
Elevation Wall Between Blocks N & F - Mar 2025
M & O Blocks – Elevation - Mar 2025
P Block: Elevation - Mar 2025
D & E Blocks: Elevation - Mar 2025
4 Acre: Flat QA Certifications - Mar 2025
4 Acre: Common Area Finishing Works - Mar 2025
4 Acre: Terrace Tiling Works For Yoga Deck - Mar 2025
4 Acre: Terrace Clay Tile Flooring Works - Mar 2025
4 Acre: Organic Waste Converter Room Finishing Works - Mar 2025
4 Acre: Sewage Treatment Plant Room - Installation Works - Mar 2025
4 Acre: Sewage Treatment Plant Room - Installation Works - Mar 2025
4 Acre: DG Room Finishing Works - Mar 2025
4 Acre: South Driveway & Compound Wall Finishing Works - Mar 2025
4 Acre: East Driveway Finishing Works & Soil Filling For Plantation Works - Mar 2025
4 Acre: North Driveway Finishing Works & Plantation Works - Mar 2025
4 Acre: North Driveway Finishing Works & Plantation Works - Mar 2025
D Block: Driveway, Lobby Entrance Steps Finishing Works - Mar 2025
4 Acre: Basement VDF Flooring - Mar 2025
4 Acre: Exit Gate & Security Room - Mar 2025
A Block: South Elevation, Entry Gate & Compound Wall - Mar 2025
A & B Blocks: 8f Block Masonry Works - Mar 2025
A & B Blocks: Above Terrace Works - Mar 2025
A Block: Elevation - View From South-East Corner - Mar 2025
Brigade Horizon Tower F: Milestone Release On Installation of Lifts - Mar 2025
Brigade Horizon Tower F: Milestone Release On Installation of Lifts - Mar 2025
Brigade Horizon Tower N: Milestone Release On commencement of Painting - Feb 2025
Brigade Horizon Tower N: Milestone Release On commencement of Painting - Feb 2025
Brigade Horizon Tower B: Milestone Release On casting of Terrace floor slab - Feb 2025
Brigade Horizon Tower B: Milestone Release On casting of Terrace floor slab - Feb 2025
Brigade Horizon Tower P: Milestone Release On commencement of fixing of Doors and windows - Feb 2025
Brigade Horizon Tower P: Milestone Release On commencement of fixing of Doors and windows - Feb 2025
Brigade Horizon Tower E: Milestone Release On Commencement of Flooring - Feb 2025
Brigade Horizon Tower F: Milestone Release On Commencement of Flooring - Feb 2025
Brigade Horizon Tower F: Milestone Release On Commencement of Painting - Feb 2025
Brigade Horizon Tower F: Milestone Release On Commencement of Painting - Feb 2025
Entry Portal - Jan 2025
G & H: Elevation - Jan 2025
I Block: Elevation - Jan 2025
J & K Blocks: Elevation - Jan 2025
L Block: Elevation - Jan 2025
M & O Blocks: Elevation - Jan 2025
N Block: Elevation - Jan 2025
N Block: Elevation - Jan 2025
P Block: Elevation - Jan 2025
O & R Blocks: Elevation - Jan 2025
P & R Blocks: Elevation - Jan 2025
Q Block: Elevation - Jan 2025
E & F Blocks: Elevation - Jan 2025
E & D Blocks: Elevation - Jan 2025
C & D Blocks: Elevation - Jan 2025
Open To Sky Light Area - Jan 2025
South Elevation - Jan 2025
East Elevation - Jan 2025
South Elevation - Jan 2025
Terrace Finishing Works - Jan 2025
Terrace Service Line Works - Jan 2025
Fire Protection System Works - Jan 2025
Basement VDF Flooring Works - Jan 2025
Ground Floor Corridor Finishing Works - Jan 2025
Basement Ceiling Service Works - Jan 2025
Basement Ceiling Service Works - Jan 2025
Basement Ceiling Service Works - Jan 2025
Toilets: Fixing Of Cp & Sanitaryware - Jan 2025
Lift Lobby + Staircase Finishing Works - Jan 2025
Staircase Finishing Works - Jan 2025
4 Acre: North Side Driveway - Jan 2025
4 Acre: South Side Driveway. And 4 Acre – West Side Driveway - Jan 2025
4 Acre: Exit Gate & Security Room - Jan 2025
A Block: South Elevation - Jan 2025
A & B Blocks: Terrace Floor Casting - Jan 2025